Reconstruction of Vesey Street
ID #HWMWTCB6:
Laura Rivera, CCL- Tel: 929- 623-4079 Email: [email protected]
- Estimated completion Date: June 2025
Current Work Operations:
Location: South of Vesey Street between Broadway and Church Street
- The steam abatement has been completed on the exposed portion of the trench.
- While excavating, a Con Edison D-faulted cable was found. A Con Edison crew came to the site and tagged the cable. The contractor is on standby, waiting for Con Edison to resolve the D-faulted cable so excavation can continue.
- The NYC DOT waiver for the Holiday Construction Emnargo was approved.
- They have been helping the 217 Broadway building manager secure DOT permits for a boom lift to facilitate façade work and expedite the removal of the scaffolding.