Reconstruction of Front Street
ID#SANDHW08 Aimee Sanders – CCL
Estimated Completion Date:- December 2024 (We have requested a time extension to April 2025. We are waiting on approval from DDC).
Current Work Operations:
- Cobblestone installation work
- Excavate roadway & pour concrete base on Front St. & Water St.
- Excavate roadway & pour concrete base on Front St. & Old Slip
- Excavate roadway & pour concrete base on Front St & Maiden Lane
- Excavate roadway & pour concrete base on Front St. & John St.
Next Phase:
- Cobblestone installation & grouting work on Front St. between John St. & Fletcher St.
- Crosswalk & ADA ramp installation work at the intersections of Fletcher St. & John St.
- Full roadway restoration asphalt & striping throughout Front St. between Fletcher St. & Old Slip
- Tree planting on Front St. & Wall St.
- Install signs throughout the project limit area on Front St.