Reconstruction of Trinity Place
ID #HWMWTCB7:
Amelia Ramos, CCL – [email protected], 516-693-3369
-Estimated completion January 2029.
Current operations: Trinity Pl. between Morris & Edgar Streets
- Water main work completed along Trinity Place from Morris to Edgar Street
- The contractor removed & replaced ECS utilities and encased conduits in concrete
- The contractor continues excavating to expose the steam main. CE specialty crew performing steam abatement work. Steam main repair and/or replacement will follow, as needed
- MFM applied for a full roadway closure on Rector St. between Trinity Place and Broadway, to perform utility work. Awaiting DOT approval. Work is anticipated to begin in January 2025, and last for approximately 6 months.
- PS 150 – Halloween Outdoor Parade: To accommodate the school, the contractor prepared the site and stopped all noisy operations during the parade on 10/31.