Reconstruction of Greenwich Street
HWMWTCB2
Phillip Stafford, CCL – [email protected], 646-374-7364
- Phase 1 (Greenwich St from Barclay St to Murray St) anticipated completion date: August 2026
- Phase 2 (Greenwich St from Murray St to Chambers St) anticipated completion date: November 2026
Current Work:
- Excavating and removing concrete from existing utilities at Greenwich St and Murray St, will allow for water main installation
- Test pits to locate utilities on Greenwich St between Murray St and Warren St, for future water main installation
- Installing a new catch basin on the west side of Greenwich St between Barclay St and Park Pl.
- Expanding excavation area on Greenwich St between Park Place and Barclay St to relocate existing telecommunications ducts for water main installation